NIGERIA has developed a troubling habit of announcing multibillion-dollar electricity projects without first demonstrating why existing infrastructure fails to deliver electricity. On 9 November 2026, Minister of Power Joseph Tegbe announced a $2 billion East-West Super Grid, promising transmission capability of 19,000 megawatts (MW) within 18 to 24 months. The announcement echoed a similarly priced proposal by his immediate predecessor, Adebayo Adelabu, barely thirteen months earlier.
But what precisely is the problem this investment intends to solve? Is Nigeria’s principal electricity challenge inadequate transmission infrastructure, insufficient generation availability, or systemic failures across the electricity value chain requiring an integrated solution?
Adelabu’s Proposal, Tegbe’s announcement
On 6 October 2025, Adelabu disclosed that the Federal Government was negotiating a $2 billion loan from the Export-Import Bank of China to construct a Super Grid linking eastern and western Nigeria. The Federal Executive Council had reportedly approved the financing proposal, intended to strengthen transmission infrastructure and attract industrial consumers back to the national grid. Tegbe’s proposed network would traverse Funtua, Gwagwalada, Ikot Ekpene, Benin, Epe and Ilorin. Presidential approval has reportedly been secured, and procurement initiated. The parallels are striking: the same administration, identical price tag and east-west transmission objective, but a different minister.
Is Tegbe implementing Adelabu’s proposal, redesigning it, or introducing another project? What became of the Chinese financing negotiations? Was any loan agreement concluded? Has an independent feasibility assessment established the project’s economic viability? The financing structure remains unclear. Nigerians deserve to know whether it involves sovereign borrowing, private investment, public expenditure or contingent liabilities that future taxpayers may inherit.
The forensic evidence the minister cannot ignore
In my earlier forensic investigation into Nigeria’s power-sector physical and financial losses, I examined 28 grid-connected power plants between April 2025 and March 2026. The findings exposed a troubling generation crisis.I classified 11 plants as Critical, with time-weighted availability of 25 per cent or less, and another nine as Poor, with availability above 25 but not exceeding 50 per cent. Altogether, 20 plants, representing 71.4 per cent of Nigeria’s grid-connected generating stations, fell within these categories.
These plants possessed approximately 9,896 MW of installed capacity, yet their combined average available capacity was only 2,467 MW. The 11 Critical plants alone accounted for 4,816 MW of installed capacity but contributed approximately 427 MW on average. Across the April 2025–March 2026 study period, national average available generation capacity was approximately 5,174 MW, while actual generation averaged just 4,312 MW. Available capacity declined from 5,400.38 MW in the fourth quarter of 2025 to 4,457.96 MW in the first quarter of 2026. Thus, only 32.7 per cent of Nigeria’s 13,625 MW installed generation capacity was available on average during that quarter. Installed capacity represents a generating plant’s rated output; available capacity reflects what it can supply under prevailing operating conditions, accounting for equipment failures, maintenance, fuel shortages and other constraints.
Some reports defending the Super Grid have described Nigeria’s installed generation capacity exceeding 13,000 MW as available for evacuation. This confuses installed capacity with operational availability. Transmission investment must be justified against electricity that generating plants can realistically produce, not merely their nameplate capacity. These findings, documented in my four-part series published in this column between 24 August and 21 September 2026, should be on Tegbe’s desk before he advances another multibillion-dollar transmission proposal.
How does a transmission network targeting 19,000 MW address Nigeria’s severe generation constraints? On 8 June 2026, TCN Managing Director Sule Ahmed Abdulaziz stated that Nigeria’s transmission network possessed 8,700 MW of wheeling capacity, against a historical peak of just 5,801.84 MW recorded on 4 March 2025. He maintained that transmission was not the principal constraint in the electricity value chain. Transmission lines do not manufacture electricity. Transformers cannot compensate for unavailable turbines. Additional corridors cannot independently restore defective generating units, guarantee gas supply, or resolve financial obligations undermining electricity production.
The minister may argue…
Continue reading the complete column on the publisher’s website.